Project team scales steep heights for excellence

Print This Page

11 September 2009

The Bulk Water Alliance has won a prestigious Engineering Excellence award for its AUD3.2 million geotechnical project to underpin the successful design and construction of the enlarged Cotter Dam.

The project is part of ACTEW Corporation's suite of water security projects to be implemented over coming years. The Bulk Water Alliance consists of ACTEW, GHD, and contract alliance partners John Holland and Abigroup.

At 80 metres high, the new dam will be Australia’s third largest concrete gravity dam – exceeded only by Warragamba and Burrinjuck Dams. The dam’s design and construction represents an historic project for the ACT and for Australian engineering.

The geotechnical project was carried out in the unusually steep work environment of the dam’s future construction site in the Cotter River valley. The BWA geotechnical team had to overcome many engineering challenges.

‘Working at height’ and ‘rope access’ training prepared geologists to abseil down cliffs to map rock defects and geological faults, drill shot holes and place explosives for seismic refraction surveys. Helicopters lifted prefabricated drilling platforms onto site.

GHD Senior Engineering Geologist, Andrew Barclay, said that to work safely in a site of significant hazards, including rock fall events made more frequent following the 2003 bushfires, BWA had to adopt procedures to manage the safety of its personnel and the community at large.

"We worked hard to ensure that safety was not compromised during the 11.5 month project. The project was completed on time and within budget, without any safety incidents or lost time to injury," Mr Barclay said.

The geotechnical data provided will play a major role in reducing the cost of the dam. Investing in the geotechnical investigations at the front end of the project has enabled BWA to design an efficient foundation excavation that also meets dam safety requirements.

The work of the geotechnical team has been independently scrutinised throughout the project. In August 2008 the expert review panel commented that: "The investigations and the design of the dam are in good hands. All involved are to be commended". In June the panel wrote that: "In our opinion the standard of geological mapping and borehole logging on this project has been very high and provides a sound basis of assessing shear strength and other relevant engineering properties".

The Cotter precinct is beloved by Canberrans as a leisure destination. BWA was conscious not only of minimising the visual and noise impact at the site, but of reaching out to share and showcase geological and archaeological findings with Canberrans. Children could touch rocks that were formed 400 million years ago around the Cotter Dam during a five-day event at the National Science Festival.

Sites of Aboriginal and European cultural heritage value were identified and participation from the Ngunnawal Elders and other cultural and heritage groups, ensured appropriate responses. Time and money was saved by carrying out test pit investigations by geotechnical staff , archaeology consultants and Registered Aboriginal Organisations concurrently.

The enlarged Cotter Dam will secure ACT’s water supply for future generations and its building will provide a major boost for the local economy, at a time when the global financial downtown is causing a drag on employment prospects and economical development.

For further information, contact:

Donna Sowry 61 2 6175 2388

GHD Library

The GHD library is a collection of relevant resources.