Bogong Hydropower Project

The Bogong Hydropower Project has been described as the “Missing Link” in a series of generation facilities that have been undertaken in the Kiewa Valley, Victoria, Australia.

As Owners Engineer, GHD undertook the detailed geotechnical investigation, development of a geotechnical baseline report (GBR) and preparation of the reference design and all tender documentation.

Through the Construction phase, GHD provided supervision services with specific responsibility for the tunnels, shafts and powerstation.

The Project takes water from the McKay Pumping Station tailrace, and delivers it at high pressure to the new Bogong Pumping Station.

The Tunnel site mobilisation began in January 2007, with GHD staff providing onsite construction supervision on all stages of works.

Tunnelling

image

GHD’s technical tunnelling solutions are characterised by innovation and a focus on our clients’ needs.

GHD’s skilled tunnel engineers are equipped to provide input during all stages of a tunnelling project from planning and design through to project management. Our experience has been enhanced through the delivery of award winning technical solutions to both contractors and client organisations throughout Australia and internationally.